SCHEDULED MAINTENANCE

Primary Dates: 13 April 2007 00:00:01 – 15 April 2007 23:59:59 GMT

Location of Maintenance: Incubatec Munich Datacenter #1

Customer impact: No impact to customer services in expected.

Maintenance summary: Work will be conducted to upgrade the Facility UPS I/O Board.
During 13 April 2007 00:00:01 – 06:00:00 GMT, 2 temporary Generators will be installed and tested alongside the present EPG system. Following successful installation and testing, these Generators will then be used to provide power to the facility PDU system during the period 14 – 15 April 2007. This will allow incubatec technicians and equipment vendors to complete the UPS upgrade.

If you have any questions or concerns about this network maintenance notification, please call or email us.

Thank you for your cooperation,
Thomas Moroder
President – incubatec

Pubblicato in:

Lascia un commento

Il tuo indirizzo email non sarà pubblicato. I campi obbligatori sono contrassegnati *

Questo sito usa Akismet per ridurre lo spam. Scopri come i tuoi dati vengono elaborati.